Canyon Kitchen & Bath
St. George remodeler handling cabinets and countertops as part of full kitchen and bath renovations.
Canyon Kitchen & Bath is a St. George remodeler that treats cabinets and countertops as parts of a whole renovation rather than as separate purchases. Kitchen work is unusually sequence-dependent, and most of the delays homeowners experience come from that sequence rather than from any individual trade being slow.
Context
The fixed constraint is that countertops cannot be measured until the cabinets are installed. A countertop is templated - measured directly against the built cabinet run, usually with a laser or a physical pattern - because the accumulated variation in a wall and a set of boxes is larger than the tolerance a stone top needs. Templating therefore happens after cabinet installation, fabrication takes time after templating, and the sink, faucet and cooktop have to be on site before templating so their cutouts can be made. Plumbing and electrical rough-in has to be finished and inspected before any of it, because those live inside walls the cabinets will cover.
So the critical path runs: demolition, rough-in, inspection, drywall and paint, flooring or its underlayment, cabinets, template, fabrication, install, then final plumbing and electrical connection. A kitchen is without a working sink for the window between cabinet install and countertop install, which is not a scheduling failure but a structural feature of the sequence. The other lesson is that long-lead selections - custom cabinets, a specific slab, an imported tile - need deciding at the beginning, because a decision deferred by a week can move the finish date by a month.
Related on the site: home builders and plumbers. See every listing under Cabinets & Countertops.
Nearby: Upholstery Doctor, Renu Auto, Pure Tech Water.
Categories
Address
1316 S 400 E, Ste C1St. George, UT 84790
Contact
- Office Phone: (435) 633-6698
Frequently asked questions
Why are countertops measured after the cabinets are installed?
Because a stone top is templated against the cabinets as actually built. The accumulated variation in a wall and a run of boxes is greater than the tolerance the top needs, so the template is taken from the real installation rather than from a drawing. Fabrication follows the template, which is why the gap between cabinet install and countertop install exists.
Does the sink need to be purchased before templating?
Yes. The sink, faucet and cooktop cutouts are made during fabrication using the actual fixtures, so those items have to be on site when the template is taken. Substituting a different sink afterwards usually means recutting or replacing the top.
What order do the trades work in on a kitchen remodel?
Broadly: demolition, then plumbing and electrical rough-in, then inspection, drywall and paint, then flooring or underlayment, then cabinets, then the countertop template, fabrication and installation, and finally the plumbing and electrical connections. Each step depends on the one before, which is why a change in the middle moves everything after it.